Cell 3 Detailed Design, Construction Project Management and Construction Quality Assurance

Client: Hi-Quality Group Pty Ltd

Discipline: Waste & Resource Management

Date: January 2020 onwards

InSitu Advisory was engaged by Hi-Quality Group to undertake a detailed design of their proposed general solid waste (non-putrescible) waste Minda landfill in Windellama, NSW.  InSitu Advisory undertook the design in full accordance with the NSW EPA Environmental Guidelines: Solid Waste Landfills, 2016.  EPA approval was achieved after the submission of a detailed Technical Specification, CQA Plan and detailed design drawing set.

InSitu Advisory were also commissioned to provide on-site independent construction quality assurance (CQA) services using experienced in-house specialist engineering staff.

The completed Cell 3 will provide ongoing waste disposal solutions for the region.